St Michaels College – Secondary Campus

Client: St Michaels College – Secondary Campus

Project:

Commentary

BluBuilt Constructions was engaged to construct the new access lift to the existing classroom block at the secondary campus.

Scope

  • Construction of new lift shaft
  • Supply, installation and commissioning of new electrical and communication feed
  • lift installation works including all finishes
  • balcony modifications to accept 1st floor access points

Challenges

Construction vehicle and equipment access to site was extremely tight, to the point that the initial tendered design detailed a blockwork lift shaft allowing in-situ construction to be undertaken. BluBuilt developed an alternate precast option requiring a detailed lift-study and pavement assessment ensuring a large capacity crane could successfully erect the panels.

Client

St Michaels College

Contract Type

LumpSum

Timing

December 2015 – February 2016