Wattle Park Pump Station

Client: Guidera O’Connor (SA Water)

Project: Wattle Park Pump Station

Commentary

BluBuilt was engaged as the subcontractor to deliver a 650m² internal fit-out as part of the City of Onkaparinga’s extensive Waterproofing the South strategy.

Scope

  • Fit-out of control/analysis room
  • Fit-out of fire rated switch-rooms
  • Fit-out of workshop
  • Fit-out of server room
  • Fit-out of store room
  • Fit-out of change rooms
  • Fit-out of wet areas

Considerations

Construction and project management had to be carried out in accordance with SA Waters’ strict quality, safety and environmental standards.

Client

Guidera O’Connor (SA Water)

Contract Type

Lump Sum

Timing

November 2012 – January 2014

Civil/Industrial/Utilities/ July 1, 2015

Waterproofing the Wes… March 16, 2015 Bolivar Main Pump Sta… July 7, 2015