BluBuilt was engaged to construct the new sporting facility for the Parafield Gardens Soccer Club. The existing clubroom facility was replaced with a structural steel, lightweight clad building approximately double the building footprint of the existing facility.
Scope
- Demolition of the existing facility
- Installation of temporary change, function and club facilities for the soccer club during construction
- Detailed earthworks and extensive underfloor services
- Construction of the new facility including open space function area, bars, kitchens, offices, canteen, change rooms and toilets
- Upgrade of car parking facilities
Challenges
The project was undertaken within strict construction timeframes.
Client
City of Salisbury
Contract Type
Lump Sum
Timing
March 2015 – July 2015