BluBuilt was engaged to construct equipment footings, ducts and associated concrete and civil works for a new 6 acre greenfield 275/66kV substation at Munno Para.
Construction of new pole, transformer and general infrastructure footings
Construction of reinforced concrete services ducts -General civil works
Tenix
Munno Para Substation
Lump Sum
September 2014 – September 2015
Challenges
Construction programming relative to the timing for delivery of key HV electrical infrastructure -Strict tolerances on footing levels and HD bolt position
All works were successfully completed within the tight contract timeframes.