Darlington Upgrade CER Building

BluBuilt was engaged to construct and fitout the new Computer Equipment Room controlling ITS for the new Darlington Upgrade Project.

Scope

  • Structural raft footings with trench piers
  • Precast concrete panels
  • Structural steelwork, mezzanine and roofing
  • Internal fitout
  • Mechanical services installation and commissioning
  • Hydraulic services installation and commissioning
  • External pavement and fencing

Challenges

Construction was undertaken in a relatively tight site with access planning successfully implemented for each stage of the building.