Korvest Fabrication Workshop

The project comprised construction of a new fabrication building with steel portal frame structure, precast dado wall with metal wall cladding, and metal roof sheeting. The project also
included associated paving, stormwater and civil works.

The scope of works included:

  • Demolition and removal of existing light poles, carpark, fencing and minor trees
  • Bulk earthworks
  • Construction of retaining walls
  • Installation of CFA piles, strip footings, and pile caps
  • Structural steel portal frame superstructure
  • Roofing and metal wall cladding
  • Precast concrete Dado wall panelling
  • Concrete slabs
  • New specialised sliding doors and roller doors
  • Epoxy flooring
  • Construction of new office with mezzanine and amenities
  • Service connections
  • Existing transformer upgrade
  • Installation of new Humeceptor and in-ground sewer pump station
  • Stormwater and groundwater systems
  • New fire ring main to service the workshop and greater site.

There was low-level contaminated waste (LLCW) on the site that we had to address. This was overcome by reducing the environmental footprint, as well as relocating the LLCW onsite.
The site was located within an operational industrial business, as Korvest’s operations on the greater site continued throughout the project. This resulted in difficulties in organising logistics, scheduling trades and managing external works, and working in and around the live environment, including trucks and forklifts. To mitigate this risk, we continuously engaged with the client, liaising with them daily, and undertook meticulous planning.